The project owner (EGOTH) is planning to renovate the existing hotel, and increase the hotel capacity by constructing a new extension. It has four interrelated objectives: Project Description
• The plot area is estimated to be 3,213 SQM
The Existing Building consists of:
-1 underground basement level,4 podium levels (Ground level to
Third Level), 11 upper floors (Fourth level to Fourteenth level), with
a total BUA of the existing building is estimated to be 37,125 SQM
The New Extension consists of:
- 3 underground basement levels, 4 podium levels connected to
the existing building (Ground level to Third Level), and Annex
tower with 11 upper floors connected to the existing building
(Fourth level to Fourteenth level)
- The total BUA for the new extension is estimated to be 11,510
SQM including the basements
- The new extension shall contain the below components: Pool
Deck in the third level, 56 keys (49 guest rooms & 7 Suites),
Restaurant & Kitchen in the 13th floor, and The 2nd